Masonry Begins - January 18th - 22nd, 2017

Masonry work began on the house on January 18th.  By January 20th; the entire kitchen bar, ⅓ of the exterior stone work, and ½ of the exterior brick were complete.  The brick is jumbo sized Acme Bristol Oak mixed brick and the stone is Acme Chopped Cream limestone.